CALL TO GET STARTED

MALLOY AVENUE SANITARY SEWER

Project Details

Client Name: City of Ferndale
Construction Cost: $472,952
This project included the installation of approximately 1,000 linear feet of 15-inch sanitary sewer main, 100 linear feet of 8-inch sanitary sewer main, and 200 linear feet of 6-inch side sewer along Malloy Avenue and Thornton Road. The new sewer main was constructed from an existing manhole located approximately 100 feet south of the Malloy Avenue and Oxford Court intersection and extended southerly approximately 800 feet along Malloy Avenue and then easterly approximately 200 feet along Thornton Road. Work included trench excavation, sanitary sewer installation, reconnection of existing sanitary side sewers to the sewer main, removal of existing structures, and HMA paving. R&E provided the design, inspection, and construction support.

GET STARTED

WE FOCUS ON INNOVATIVE DESIGN AND CUSTOMER SERVICE.

SCHEDULE A CALL TODAY TO GET STARTED ON YOUR PROJECT.