SR9 Township Trenchless Sanitary Sewer Improvements
Project Details
Client Name: City of Sedro-Woolley, WA
Construction Cost: Approximately $3.62 Million (local funding)
The scope of work performed for this project included the design, plan and specification development, contract administration and project inspection of the installation of approximately 4,000 LF of 24-inch and 15-inch vitrified clay sanitary sewer installed utilizing Guide Pilot Tube MicroTunneling. Additionally, 600 LF of 12-inch HDPE was installed using Horizontal Directional Drilling (HDD) technology.