East Grover St. Reconstruction
Project Details
Client Name: City of Lynden, WA
Construction Cost: $2.7 Million
Project Manager: Larry Leicht, Project Manager
This project consisted of street improvements to Grover Street from Lawrence to the RR tracks, Nooksack Avenue from Grover to Drayton, Front Street from Bender to Tierney, and Lynn Street from Front to Grover. The project included: 600 lineal feet of sanitary sewer replacement, 1180 lineal feet of sanitary sewer lining, and 6100 lineal feet of water main replacement. Work included removal of existing pavement, curbs and sidewalks, grading, installing storm drainage, sanitary sewers, and water mains, placing gravel base and crushed surfacing, asphalt concrete paving, installing curbs, gutters, and sidewalks and landscaping. This project is part of the American Recovery and Reinvestment Act (ARRA).