FOXTAIL STREET GAP ELIMINATION
Project Details
Client Name: City of Lynden
Construction Cost: $367,000
R&E provided design services for the construction of approximately 400 feet new roadway to connect the existing portions of Foxtail Street between Eastwood Way and Bradley Meadows Lane. The work included roadway, storm drain evaluation, water main, and sanitary sewer design, including franchise utility and City coordination. Construction of this project includes curb, gutter, sidewalk, pedestrian improvements, 320 linear feet of 8-inch diameter water main, stormwater improvements, and 375 linear feet of 8-inch diameter sanitary sewer main. R&E also provided project inspection and construction management.